Project Planning for Complex Construction Projects

PROVIDING BOARD LEVEL CLARITY & PROJECT TEAM TRACTION. FAST

We decompose project complexity into solvable chunks, challenge assumptions, and translate board intent into site execution — so risk stops compounding and the program follows an explicit plan.

Schedule an Initial Sprint Consultation
construction-malaysia-02

Trusted Project Advisory

lendlease_logofcc_logokiwirail_logoawm_logobloc_logoconstruction_control_logocore_project_group_logomacquarie_group_logointerislander_logoadco_logo

Our Experience

baranagroo-south-02

We provide executive level clarity together with site‑level engagement for effective construction project management - we drive for an understanding of what’s critical, identify controlling workflows, and align the schedule with an updated project plan.
 

Contact Us for a Consultation

15

Global Coverage -  Engaged in Projects 
Multiple Countries

250+

Project Planning Training Courses
Delivered Globally

30+

Years of Delivering Complex Projects

Challenges with Project Delivery

A construction project delay is rarely bad luck — it’s typically a misalignment between the plan, a disconnection with the original assumptions, complex schedule logic, and delayed decision making.

For owners, contractors, and project management consultancies, the issues below are the usual suspects and pain points:

  • The Executive Leadership Team are frustrated that when reviewing the project the risk register doesn’t touch the critical path.
  • Executive level dashboards read green while the sense is that work is late with continued slippage expected.
  • The Project Director is continually frustrated by a schedule that continues to grow - but crews are still blocked and work continues to be delayed.
  • The project team is constantly reacting to critical paths that keep oscillating and float that seems to evaporate.
  • Design deliverables, procurement, supply chains and permits aren’t modelled as constraints, as a result the Project Leadership Team are faced with dates that are “optimistic by default”.
  • The Project Owner gets frustrated when the project team’s and contractor’s narratives continuously don’t reconcile.
  • Our baselines and current programs are diverging; our lack of schedule change control hides reality.

At What’s Critical we are able to:

  • Reconnect risk to schedule logic with diagnostics that show where risk actually moves dates.
  • Drive for one truth so reporting matches reality enabling critical decisions to be made.
  • Assist teams stabilise float by simplifying the project schedule logic, ensuring work sequences are represented accurately and “make sense”
  • Identify the construction productivity challenges and ensure that the real workflows are integrated and address progress blockers.
  • Ensure that critical elements are included in an integrated plan so slippage is visible — and preventable.
  • Communicate one truth in two dialects - board‑grade clarity up, site‑level to drive execution and traction downstream.
  • Help establish an honest baseline and reporting rules that reveal drift early so recovery starts sooner.
matthew_boot_profile_image_2

Unfortunately the construction industry has confused scheduling with planning.

We make the plan explicit and document it — strategy, assumptions, work flows, resource constraints — with a schedule as the output of the planning, not the construction schedule being mistaken for planning. ”

Matthew Boot - Founder, What’s Critical